  • 1 : Long Seam Weld Pipe Plant - Khartoum, Sudan
  • 2 : Aluminum Extrusion Plant - Khartoum, Sudan
  • 3 : Pirishtina Road Rehabilitaion - Kosova (for EPIK)
  • 4 : Ground Facilities for Space Imaging - Ankara
  • 5 : Pipe Coating Plant - Khartoum, Sudan
  • 6 :130 TPH Crushing Plant and 120 TPH Asphalt Plant - Sudan
  • 7 : Water Bottleing Plant - Suleymaniyah, Iraq
  • 8 : Ifraz Water Treatment Plant - Erbil, Iraq
  • 9 : International School of Choiefat - Erbil, Iraq
  • 10 : Overpass for International School of Choiefat - Erbil, Iraq
  • 11 : Khormor - Erbil 24" Gas Pipeline - Erbil, Iraq
  • 12 : LPG Plant Infrastructure - Erbil, Iraq
  • 13 : Dokan Water Treatment Plant Clarifiers- Suleymaniyah, Iraq
  • 14 : Dokan Water Treatment Plant Electromechanical Works - Suleymaniyah, Iraq
  • 15 : Contruction of 4 1 villas - Bodrum - Turkey
  • 16 : Taq Taq Oil Field Surface Facilities - Koya, Iraq
  • 17 : Governorate Building - Suleymaniyah, Iraq

Ongoing Projects

  • 1 : Road and Bridge Widening - Suleymaniyah, Iraq
  • 2 : Water Supply Project - Suleymaniyah, Iraq
  • 3 : Sports complex - Halabja, Iraq
  • 4 : 500 MW Power Plant Installation - Dohuk, Iraq
  • 5: Water Treatment Plant Eextension - Dokan - Iraq

Project Details


PROJECTCLIENTDATE OF STARTDATE OF COMPLETIONCONTRACT TOTAL
Road and Bridge Widening Suleymaniyah, Iraq Suleymaniyah Governorate July 2008 Nov 2010 16,700,000 USD
Water Supply Project Water Directorate Suleymaniyah Dec 2009 Nov 2010 23,150,000 USD
Halabja Sports Complex Suleymaniyah Governorate August 2008 Nov 2010 11,770,000 USD
500 MW Power Plant Installation, Dohuk, Iraq ABB Feb-10 Feb-11 5,600,000 Euros
WTP Filter Building Extension Dokan, Iraq Suleymaniyah Governorate May-10 Ian-11 7,800,000 USD